Project status report template: weekly and monthly

A project status report tells stakeholders where the project stands, what changed and what you need from them, in a few minutes of reading. Below are a weekly and a monthly template, how to use RAG status honestly, and how to have a coding agent draft the report from commits and pull requests.

Updated 2026-11-25 · tested with Claude Code and Codex

Weekly status report template

# Project Atlas: weekly status, week of 2026-11-16
Overall: AMBER   (last week: GREEN)
Why amber: payment provider sandbox access is two weeks late.

## Done this week
- Shipped invoice export (PR #482)
- Load test of the search API passed the agreed target

## Next week
- Start EU data residency work
- Close 6 open bugs from the beta

## Blocked
- Payment sandbox access: waiting on vendor. Owner: <name>

## Risks
| Risk | Likelihood | Impact | Mitigation | Owner |
|---|---|---|---|---|
| Launch date slips if sandbox arrives after 2026-12-01 | Medium | High | Build against mocks now | <name> |

## Decisions needed
- Approve moving the beta end date to 2026-12-12 (by Friday)

## Key dates
- Beta end: 2026-12-05 (at risk)
- Launch: 2026-01-15

Example from our demo project, made-up data.

The monthly status report template

A monthly report is for people further from the work. Keep it shorter on tasks and longer on direction:

# Project Atlas: monthly status, November 2026
Overall: AMBER   Scope: GREEN   Schedule: AMBER   Budget: GREEN

## Summary
Three sentences: where we are against the plan and why.

## Milestones
| Milestone | Planned | Forecast | Status |
|---|---|---|---|

## Highlights
## Top risks and issues (with owners)
## Decisions needed from you (with a date)
## Next month

RAG status that means something

Always write one line on why the colour is what it is, and show last week's colour so a change is visible. A report that stays green until the week before launch is the most common way status reports fail.

Draft it with a coding agent

Most of a weekly report is already in your repo: merged pull requests, closed issues, commit messages and the team's notes. Claude Code or Codex can draft it. An example prompt:

Draft this week's status report using the template in docs/status-template.md.
Sources: pull requests merged since last Monday, issues closed or opened,
and docs/status-notes.md. Copy dates and numbers verbatim, link each item
to its PR or issue, and list anything you are unsure about under
"To check". Do not set the RAG status; leave it for me.

A person reviews the draft, sets the status and the decisions needed, and sends it. The agent knows what shipped; only you know how the stakeholders will read it. Rules for the agent can live in your project instructions: see the CLAUDE.md / AGENTS.md guide.

On calls

The status report is what stakeholders quote back at you on the next call: "you said the beta ends on the 5th". Keep the dates and numbers from it in your project facts file so you can answer with the same figures. FlexQ listens to the call on your computer and shows a short cue from your project folder when someone asks you a question; the facts come from a file your coding agent keeps (project facts file template). See the AI meeting assistant or FlexQ for work calls.

Download FlexQ for macOS or Windows. How it handles your files is set out in the privacy policy.

FAQ

What should a project status report include?

The overall status with a reason, what was done, what is next, what is blocked, risks with owners, decisions needed from the reader, and key dates.

What is the difference between a weekly and a monthly status report?

A weekly report is for the people close to the work and lists tasks, blockers and decisions. A monthly report is for people further away and focuses on milestones, risks and direction.

What does RAG status mean?

Red, amber, green. Green means on track, amber means at risk with a recovery plan or a decision needed, and red means a commitment will be missed without a change.

Can AI write a project status report?

It can draft one. Claude Code or Codex can collect merged pull requests, closed issues and notes into the template. A person should set the status, check the dates and send it.

More